Home Indemnity Insurance WA: The 7-Year Rule for Owner Builders

Quick Answer

Selling an owner-built home in WA within seven years of the building permit is an offence unless you obtain home indemnity insurance. What the rule covers, who holds the duty and when the clock starts.

Home Indemnity Insurance WA: The 7-Year Rule for Owner Builders

While you build

No construction-stage duty stated
The WA Government page states the home indemnity requirement in its selling section, tied to a sale within seven years, and does not state a construction-stage duty for an owner builder.

Selling within 7 years

Insurance required
Sell within seven years of the building permit and you must obtain home indemnity insurance and give the certificate to the purchaser before settlement.

Value thresholds

Above $20,000
Residential building work valued over $20,000 must be covered, and Class 10a work such as sheds, carports and private garages carries a $50,000 threshold.

$20,000

Value of residential building work above which home indemnity insurance applies

$50,000

Threshold for Class 10a buildings such as sheds, carports and private garages

7 years

From the building permit, the period in which selling triggers the requirement

Jump to Who holds it The seven-year rule Thresholds The approval FAQs

In short

  • Selling an owner-built dwelling within seven years of the building permit is an offence in Western Australia unless you obtain home indemnity insurance.
  • The clock runs from the date the building permit was granted, not from the day you finish building.
  • Work valued over $20,000 must be covered, with a $50,000 threshold for Class 10a buildings such as sheds, carports and private garages.
  • Associated work on its own, such as a pergola, fence or swimming pool, is outside the requirement described on the owner-builder page.

Home indemnity insurance is the cover most owner builders in Western Australia first hear about at the worst possible moment: when a buyer’s settlement agent asks for a certificate. The confusion is understandable, because the requirement is written around the sale of an owner-built home rather than the building of it. This guide sets out who the duty falls on, when it reaches you, and what the two current sources do and do not say.

Who has to hold home indemnity insurance in WA

On a contracted build, the duty belongs to the builder. Building and Energy’s reminder about home indemnity obligations states that before undertaking residential building work valued over $20,000, builders must obtain a home indemnity insurance certificate for the proposed work before claiming any payment from the owners or commencing work under the contract, and provide a copy to the owner and to the permit authority as part of the building approval process.

That sequencing matters if you are working out whether the rule applies to you. The builder’s obligation is triggered by the contract, and it is discharged before money moves: no certificate, no payment, no start. It is not a general duty to hold cover for the sake of holding it.

An owner builder is not in that position. You are not engaged under a residential building contract to build someone else’s home, so the builder-side sequence does not describe your project. What applies to you is the selling rule in the next section.

The owner builder trigger: selling within seven years

The WA Government’s owner-builder page puts the rule plainly, and it is stronger than most owners expect. Selling an owner-built dwelling within seven years of the date on which the building permit was granted is an offence, with a penalty of $10,000, unless you obtain home indemnity insurance.

Building and Energy describes the same trigger in practical terms: owner builders must obtain home indemnity insurance if they wish to sell their property within seven years from the time the building permit was granted, and the certificate must be provided to the prospective purchaser before settlement occurs.

Notice where the clock starts. It starts at the date the building permit was granted, not at practical completion, not at the date you move in, and not at the date a buyer makes an offer. An owner builder who took a permit in 2021 and sells in 2027 is inside the window even though the house has been finished for years.

Notice also that the requirement is framed around a sale rather than a stage of the build. The certificate has to exist before settlement, which is a long way after the permit date, and it has to reach the purchaser rather than sit in your filing cabinet.

The reminder exists for a reason worth naming: the obligation is easy to miss because it falls years after the work that created it. Building and Energy’s reminder is organised around the contract stage for builders and the permit and sale stages for owner builders.

The distinction that catches people out

Building and Energy lists the owner-builder obligation under the building permit application stage, which makes it look like something you deal with at the start of the project. The trigger it describes is a sale within seven years. If a sale is on the table, the certificate has to exist before settlement, which is well after the permit was granted.

What the $20,000 and $50,000 thresholds cover

The WA Government’s owner-builder page states that all residential building work valued over $20,000 (except for a Class 10, which is $50,000) must be covered by home indemnity insurance, however home indemnity insurance is not required for associated work, such as building only a pergola, fence or swimming pool.

For Class 10a buildings, including sheds, carports and private garages, the same page sets the threshold for the building work at $50,000.

Two practical points follow. First, the word only in the associated work sentence is doing real work: the exclusion is for a project that is nothing but associated work, not a way to carve a pergola out of a larger house build. Second, the source is inconsistent on class wording, saying a Class 10 in the insurance sentence and Class 10a buildings where it names sheds, carports and private garages. Treat Class 10a as the operative description for the permit threshold, and read the insurance sentence as written.

Where the home indemnity duty sits in Western Australia
QuestionRegistered builderOwner builder
Who carries the dutyThe builder performing the workThe owner-builder, on selling within the window
What triggers itPerforming residential building work valued over $20,000Selling within 7 years of the building permit
When the certificate is neededBefore claiming a payment or commencing work, and for the permit authorityProvided to the purchaser before settlement
Where it is statedBuilding and Energy reminderWA Government owner-builder page; Building and Energy reminder

The page runs it as step 3 and step 4: apply for owner builder approval with LGIRS, then apply to your local government authority for a building permit. Because the seven-year period is measured from the permit, the order of those two steps decides the date that matters.

Where the owner builder approval sits

The WA Government page puts the approval ahead of the permit: an owner builder approval is required prior to applying for a building permit from your local government authority. It also treats the two routes as alternatives, stating that a registered building contractor or owner-builder approval may be necessary if a building permit is required and the estimated value of the building work exceeds $20,000.

That is the useful part for planning. The approval comes before the permit application, and the permit date is the date the seven-year window runs from, so the order of those two steps determines how long the selling restriction applies to you. If you are unsure which route your project needs, the Building Services Board and your local government authority are the bodies that can confirm it for your circumstances.

What to do before you start

  1. Work out the value of the residential building work and compare it with the $20,000 threshold, using $50,000 for Class 10a buildings.
  2. Check whether the project is associated work on its own, such as a pergola, fence or swimming pool, because that sits outside the requirement described on the owner-builder page.
  3. Apply for owner builder approval before applying for the building permit, since the approval comes first.
  4. Record the date the building permit is granted. That date, not completion, starts the seven-year period.
  5. If you intend to sell inside that period, obtain home indemnity insurance and provide the certificate to the purchaser before settlement.

Building in Western Australia?

The approval, the permit and the course are three separate steps, and the approval comes first.

FAQs

Does an owner builder in WA need home indemnity insurance while building?

The WA Government’s owner-builder page states the home indemnity requirement in its selling section, tied to a sale within seven years, and does not state a construction-stage duty for an owner builder. The stage-by-stage sequence that Building and Energy sets out for certificates applies to builders claiming a payment or commencing work under a contract.

When exactly does the seven years start?

From the date the building permit was granted. Both current sources measure the period from that date: the owner-builder page refers to selling within seven years of the date the building permit was granted, and Building and Energy refers to seven years from the time the building permit was granted. It does not run from completion.

What value of work attracts home indemnity insurance in WA?

The WA Government’s owner-builder page states that all residential building work valued over $20,000 must be covered, and that for Class 10a buildings including sheds, carports and private garages the threshold for the building work is $50,000.

Is a pergola, fence or swimming pool covered by the threshold?

The owner-builder page states that home indemnity insurance is not required for associated work, such as building only a pergola, fence or swimming pool. The word only matters: the exclusion describes a project that is nothing but associated work.

Who does the certificate go to when I sell?

The purchaser. Building and Energy states that the home indemnity insurance certificate must be provided to the prospective purchaser of the home before settlement occurs.

Does the builder or the owner builder hold the policy on a contracted build?

The builder. Building and Energy requires builders undertaking residential building work valued over $20,000 to obtain a home indemnity insurance certificate before claiming any payment from the owners or commencing work under the contract, and to provide a copy to the owner and to the permit authority as part of the building approval process.

Does the owner builder approval come before the building permit?

Yes. The WA Government page states that an owner builder approval is required prior to applying for a building permit from your local government authority.

Is owner builder approval the same thing as builder registration?

The WA Government page treats registered building contractors and owner-builder approval as alternatives, stating that a registered building contractor or owner-builder approval may be necessary if a building permit is required and the estimated value of the building work exceeds $20,000. If you need to know which route applies to your project, confirm it with the Building Services Board or your local government authority.

Sources checked

  • WA Government, Owner-builder approval (value thresholds, Class 10a, associated work, the seven-year selling rule and its penalty, approval before building permit), last updated 16 September 2026, read 20 November 2026: wa.gov.au
  • Building and Energy, Home indemnity insurance – a reminder about your obligations (builder certificate timing, owner-builder sale within seven years, certificate to the purchaser before settlement), last updated 20 May 2025, read 20 November 2026: wa.gov.au

Ready to Start Your Owner Builder Journey?

Complete your Owner Builder Course online with Owner Builder Centre (RTO 91528). Approved courses for NSW, QLD & WA. Fast certification, enrol today.